How to plan a 30-day dredge rental

A 30-day rental gives you a calendar window. To see whether your pond job fits, work out the sediment volume and count the shifts when the dredge crew, receiving area and haul trucks can all work. Those two numbers give you a daily target to discuss before you book.

Turn the scope into cubic yards

Suppose a pond owner wants sediment removed from a rectangular area 120 feet long and 90 feet wide. Measurements suggest an average cut of nine inches. In feet, that cut is 0.75. Multiply the three dimensions and divide by 27 to convert cubic feet to cubic yards.

120 × 90 × 0.75 ÷ 27 = 300 cubic yardsEstimated sediment in place, before pumping or dewatering.

On an irregular pond, divide the work area into smaller sections, calculate each one and add them together. Write down where the thickness measurements came from. If the nine inches is a guess from a single spot, tell the estimator what still needs measuring.

Count the shifts you can actually use

In this example the landowner allows weekday work, leaving 20 shifts in the proposed rental window. The crew assigns two to setup and removal and holds three for weather or interruptions. That leaves 15 shifts to move the estimated 300 cubic yards.

The bid needs 20 in-place cubic yards per working shift. That figure describes what this example job requires. A pump moves water along with sediment. Gallons of slurry pumped and truckloads of wet material cannot tell you, by themselves, how much sediment came out of the pond. Agree with the owner on how the finished cut will be measured.

Walk the route to the receiving area

Measure from the farthest planned dredge position to the place where material will discharge. Trace the turns around buildings and crossings and record the rise to the endpoint. A straight line drawn across a site plan can miss a detour that uses a substantial part of the pipe package.

Our Weston rental includes a GeoForm Dino6, a Delco trailer and approximately 700 feet of discharge line. Send the measured route so we can review the length, lift and fittings for your job. Include a launch photo and tell us about liners or debris. See the rental equipment.

Check what happens when the receiving area fills

Ask the dewatering or hauling contractor how much material they can receive each shift, who manages the water and when finished material can leave the site. If the receiver closes Friday afternoon, the dredge crew needs to know before planning a Saturday shift. Put the access hours and the names of the responsible companies on the same schedule.

For Wisconsin projects, the DNR uses information about the proposed dredging method, sediment volume and disposal location in its pre-application review. Check the process for your site as you build the schedule. Wisconsin DNR dredging guidance.

Ask for a quote against that schedule

Send the site location, preferred dates, estimated sediment volume, planned shifts, discharge route and who will operate the dredge. Flag any open approvals or disposal questions. Ask for the planned pickup and return, freight, included equipment and operating terms in writing so you can compare the quote with the bid. Request a monthly dredge rental quote.